LANARKSHIRE · 3 MW GPU DATA CENTRE · GRID-CONNECTED OPERATOR
Grid-connected operator
The same 3 MW site connected to the grid, with no wind, solar or battery, and an operator that runs all of its own work. At 2025 GB prices, coordination lowers the electricity bill by switching idle nodes off, moving deferrable work to cheaper hours and keeping the peak under a lower agreed capacity.
Headline result · 2025 prices
Annual electricity bill
Without coordinationWith coordination
- Wholesale price 2025
- £79.87/MWh mean
- Mean unit price
- 17.1 p/kWh before fixed charges
- Agreed capacity charge
- 8.66 p/kVA/day
- Red band
- 16:30–19:30 weekdays · 3.935 p/kWh
Where the saving comes from
Coordination saves most where the fleet is used least, because idle nodes can switch off. Moving work in time adds little at 2025 prices; for the busiest fleet the saving comes mainly from a lower agreed capacity.
Using less electricityMoving work in timeCapacity and fixed charges
Peak shaving
The import limit is lowered step by step with coordination on. The bill falls until deferred work no longer fits; below that point tasks fail in large numbers. The marked row is the lowest bill plus lost service without unserved energy.
| Import limit | Peak import | Agreed capacity | Bill | Failed tasks | Lost service |
|---|---|---|---|---|---|
| Without coordination | 1.537 MW | 1,620 kVA · HV3 | £2.12M | 0 | £0k |
| Coordination without prices, no limit | 1.318 MW | 1,390 kVA | £1.64M | — | — |
| no limit | 1.701 MW | 1,800 kVA · HV3 | £1.64M | 2,368 | £7k |
| 1.537 MW | 1.534 MW | 1,620 kVA · HV3 | £1.64M | 1,471 | £13k |
| 1.460 MW | 1.458 MW | 1,540 kVA · HV3 | £1.64M | 1,340 | £5k |
| 1.384 MW | 1.381 MW | 1,460 kVA · HV3 | £1.63M | 1,158 | £5k |
| 1.307 MW | 1.305 MW | 1,380 kVA · HV3 | £1.63M | 896 | £5k |
| 1.230 MW | 1.228 MW | 1,300 kVA · HV3 | £1.63M | 862 | £3k |
| 1.153 MW | 1.152 MW | 1,220 kVA · HV3 | £1.63M | 625 | £1k |
| 1.076 MW | 1.075 MW | 1,140 kVA · HV3 | £1.63M | 626 | £1k |
| 0.999 MW | 0.999 MW | 1,060 kVA · HV3 | £1.59M | 4,258,940 | £3,350k |
| 0.922 MW | 0.922 MW | 980 kVA · HV2 | £1.45M | 7,197,409 | £9,220k |
A week of operation
Hourly import of the site without and with coordination, and the hourly unit price the operator pays. Shaded hours are the DUoS red band; darker hours also carry the Capacity Market charge.
Without coordinationWith coordinationUnit price, £/MWhRed bandCapacity Market hours
How the bill is built
Every hour's import pays the unit price; the agreed capacity and the residual band set the annual capacity and fixed charges.
| Component | Basis | 2025/26 rate |
|---|---|---|
| Wholesale energy | Hourly GB day-ahead price × line loss factor | £79.87/MWh mean × 1.025 |
| DUoS unit charge | Red 16:30–19:30 weekdays; amber; green | 3.935 / 0.286 / 0.006 p/kWh |
| Capacity Market | 16:00–19:00 working days, November to February | £177.4/MWh |
| BSUoS | Every MWh, by season | £10.74 / £15.69 per MWh |
| Policy levies and supply costs | Renewables Obligation, FiT, CfD, nuclear RAB, CCL, supplier costs | £66.25/MWh |
| DUoS capacity charge | Agreed capacity, kVA | 8.66 p/kVA/day |
| DUoS fixed and TNUoS residual | By residual band of the agreed capacity; band 4 above 1,800 kVA | £75k a year in band 3, £198k in band 4 |
| TNUoS locational demand | Triad periods, zone 2 Southern Scotland | zero |
Reading the result
- Moving deferrable work to cheaper hours saves 0.1–0.7% of the bill: about £91 of every MWh is a flat levy or charge, and 2025 wholesale prices vary moderately. Price-led scheduling without a limit also raises the peak, so it works together with peak shaving.
- For the busiest fleet, most of the saving is the step from residual band 4 to band 3 when the agreed capacity falls below 1,800 kVA. A site already below the boundary, or one whose agreed capacity is fixed at its design capacity, does not receive it; without capacity and fixed charges the savings are £65k, £242k and £472k a year.
- Agreed capacity is the peak hourly import divided by a power factor of 0.95. Meters record half-hourly demand, which can be slightly higher than the hourly peak.
- The scheduler sees each day-ahead price once it is published and the price a week earlier beyond that. All of 2025 uses the 2025/26 rates.