ElecTraceComputeCOMPUTE–ELECTRICITY COORDINATION

LANARKSHIRE · 3 MW GPU DATA CENTRE · GRID-CONNECTED OPERATOR

Grid-connected operator

The same 3 MW site connected to the grid, with no wind, solar or battery, and an operator that runs all of its own work. At 2025 GB prices, coordination lowers the electricity bill by switching idle nodes off, moving deferrable work to cheaper hours and keeping the peak under a lower agreed capacity.

Explore the resultsRead the WikiSee the off-grid site

Headline result · 2025 prices

Annual electricity bill

85% of card-hours running · saves £195k (7.4%)
£2.64M
£2.45M
67% of card-hours running · saves £248k (10.7%)
£2.32M
£2.07M
48% of card-hours running · saves £485k (22.9%)
£2.12M
£1.63M

Without coordinationWith coordination

Calendar 2025 GB day-ahead prices with the 2025/26 SP Distribution HV charges. Without coordination every task runs at release and all nodes stay on; with coordination training and offline inference are deferred within their completion windows, idle nodes switch off and the peak is kept under a lower agreed capacity. No unserved energy in any case. The off-grid site is compared with these same bills. How the bill is built →
Wholesale price 2025
£79.87/MWh mean
Mean unit price
17.1 p/kWh before fixed charges
Agreed capacity charge
8.66 p/kVA/day
Red band
16:30–19:30 weekdays · 3.935 p/kWh

Where the saving comes from

Coordination saves most where the fleet is used least, because idle nodes can switch off. Moving work in time adds little at 2025 prices; for the busiest fleet the saving comes mainly from a lower agreed capacity.

85% of card-hours running£195kUsing less electricity £63k · Moving work in time £2k · Capacity and fixed charges £130k · Variable charges 171.16 → 171.00 £/MWh
67% of card-hours running£248kUsing less electricity £226k · Moving work in time £15k · Capacity and fixed charges £6k · Variable charges 171.20 → 169.86 £/MWh
48% of card-hours running£485kUsing less electricity £462k · Moving work in time £11k · Capacity and fixed charges £13k · Variable charges 171.24 → 170.06 £/MWh

Using less electricityMoving work in timeCapacity and fixed charges

Peak shaving

The import limit is lowered step by step with coordination on. The bill falls until deferred work no longer fits; below that point tasks fail in large numbers. The marked row is the lowest bill plus lost service without unserved energy.

Import limitPeak importAgreed capacityBillFailed tasksLost service
Without coordination1.537 MW1,620 kVA · HV3£2.12M0£0k
Coordination without prices, no limit1.318 MW1,390 kVA£1.64M——
no limit1.701 MW1,800 kVA · HV3£1.64M2,368£7k
1.537 MW1.534 MW1,620 kVA · HV3£1.64M1,471£13k
1.460 MW1.458 MW1,540 kVA · HV3£1.64M1,340£5k
1.384 MW1.381 MW1,460 kVA · HV3£1.63M1,158£5k
1.307 MW1.305 MW1,380 kVA · HV3£1.63M896£5k
1.230 MW1.228 MW1,300 kVA · HV3£1.63M862£3k
1.153 MW1.152 MW1,220 kVA · HV3£1.63M625£1k
1.076 MW1.075 MW1,140 kVA · HV3£1.63M626£1k
0.999 MW0.999 MW1,060 kVA · HV3£1.59M4,258,940£3,350k
0.922 MW0.922 MW980 kVA · HV2£1.45M7,197,409£9,220k

A week of operation

Hourly import of the site without and with coordination, and the hourly unit price the operator pays. Shaded hours are the DUoS red band; darker hours also carry the Capacity Market charge.

0.000.881.750200400Import, MWUnit price, £/MWhMon 8Tue 9Wed 10Thu 11Fri 12Sat 13Sun 14

Without coordinationWith coordinationUnit price, £/MWhRed bandCapacity Market hours

How the bill is built

Every hour's import pays the unit price; the agreed capacity and the residual band set the annual capacity and fixed charges.

ComponentBasis2025/26 rate
Wholesale energyHourly GB day-ahead price × line loss factor£79.87/MWh mean × 1.025
DUoS unit chargeRed 16:30–19:30 weekdays; amber; green3.935 / 0.286 / 0.006 p/kWh
Capacity Market16:00–19:00 working days, November to February£177.4/MWh
BSUoSEvery MWh, by season£10.74 / £15.69 per MWh
Policy levies and supply costsRenewables Obligation, FiT, CfD, nuclear RAB, CCL, supplier costs£66.25/MWh
DUoS capacity chargeAgreed capacity, kVA8.66 p/kVA/day
DUoS fixed and TNUoS residualBy residual band of the agreed capacity; band 4 above 1,800 kVA£75k a year in band 3, £198k in band 4
TNUoS locational demandTriad periods, zone 2 Southern Scotlandzero

Reading the result

  • Moving deferrable work to cheaper hours saves 0.1–0.7% of the bill: about £91 of every MWh is a flat levy or charge, and 2025 wholesale prices vary moderately. Price-led scheduling without a limit also raises the peak, so it works together with peak shaving.
  • For the busiest fleet, most of the saving is the step from residual band 4 to band 3 when the agreed capacity falls below 1,800 kVA. A site already below the boundary, or one whose agreed capacity is fixed at its design capacity, does not receive it; without capacity and fixed charges the savings are £65k, £242k and £472k a year.
  • Agreed capacity is the peak hourly import divided by a power factor of 0.95. Meters record half-hourly demand, which can be slightly higher than the hourly peak.
  • The scheduler sees each day-ahead price once it is published and the price a week earlier beyond that. All of 2025 uses the 2025/26 rates.