PROJECT RECORD 47 · UKS004
Quest Park Data Centre Campus
England · Pre-application or consultation
Reported capacity
Claims use different boundaries and may describe overlapping phases or the whole campus. Values below are not additive, and are not an estimate of remaining construction or incremental grid demand.
IT/compute
720 MW
Retained source claims (may be historical or conflicting)
- 720 MWReported planning or campus figure; source stage may remain unresolvedit_loadfourbuildingsx180MWIT, each3x60MWIThalls; containedin1000MWfacilityindicativeatcurrentPUE, sourceauthorassumption subjecttodesignrevisionnsip_preapplicationClaim source · 2026-04 ↗
- 720 MWReported planning or campus figure; source stage may remain unresolvedIT_loadQuest Park Data Centre Campussource-stage unresolvedClaim source · 2026-04 ↗
Facility demand / power options
1,000 MW (design disclosure)
Retained source claims (may be historical or conflicting)
- 1000 MWReported planning or campus figure; source stage may remain unresolvedwhole_facility_designQuest Park Data Centre CampusdesignClaim source · 2026-04 ↗
- 1000 MWReported planning or campus figure; source stage may remain unresolvedwhole_facility_designcombinedpowerrequirementfourDCbuildings, four250MWcomponentsplanneddesign; wholeDCbuildingspowernotallpublicgridimportdesignClaim source · 2026-04 ↗
Grid/supply
200 MW (source-reported connection)
Retained source claims (may be historical or conflicting)
- 200 MWReported planning or campus figure; source stage may remain unresolvedgrid_connection_disclosedQuest Park Data Centre Campussource_claimed_connectionClaim source · 2026-04 ↗
- 200 MWReported planning or campus figure; source stage may remain unresolvedcontracted_grid_connectioninitialNESOconnection signedfordeliveryOctober2034, withfutureincreaseabilityapplicantstatementofagreement; actualcontractnotattached; alreadyexistingUKS004source-stage unresolvedClaim source · 2026-04 ↗
Reported MW · basis unknown
No selected summary claim
Retained source claims (may be historical or conflicting)
- 200 MWReported planning or campus figure; source stage may remain unresolvedea_associated_installed_capacityCustomer/DNO supplied queue-item capacity, possibly stage or technology element; not certified maximum importMW unit from NESO explanatory FOI, not added to original XLSX raw fieldsource-stage unresolvedClaim source ↗
- 200 MWReported planning or campus figure; source stage may remain unresolvedunknownunspecifiedsource-stage unresolvedClaim source · 2026-04 ↗
Apparent power · MVA
Not disclosed
- IT capacity qualification: nsip preapplication.
- Facility boundary: whole_facility_design; design.
Location & development stage
- Stage interpretation
- Pre-application or consultation
- Place / location reference
- Bedford
- Position precision
- Approximate locality
- Map position
- 52.1346, -0.4663 (latitude, longitude)
Ampthill Road is a road name in a location stated as Bedford/Central Bedfordshire. Matching Ampthill town upgrades a street token into an unsupported town coordinate. Corrected to the source-named locality; not a site coordinate.
Map points are not surveyed parcel boundaries or electricity connection nodes. The stage is a source-based interpretation at the evidence cutoff, not a current-status check.
Project evidence
These links identify the original publishers. A source may concern a different permit, phase or capacity boundary; use it with the qualifications above.
Cite this record
ElecTrace (2026-10-14). Quest Park Data Centre Campus. UK Data Centre Planning Database, version 1.0.0, project record UKS004. Evidence cutoff 2026-09-22. https://electrace.uk/compute/uk-data-centres/projects/UKS004
Add your access date. Map number 47 is specific to this release; use the record identifier UKS004 and URL for citations.