Scheduling replay: a week at the off-grid GPU site
Hour by hour, the scheduler at the Lanarkshire data centre balances wind and solar output, a battery, biomethane backup engines and the tasks its tenants submit. This page replays three weeks of 2024 with the actual weather, the ECMWF forecasts as they were issued at the time and a real multi-tenant task record. Press play or drag the slider to move through the week.
Power
MW. The coloured layers add up to the site's demand. The solid line is wind and solar available; the dashed line is the forecast the scheduler is using now.
Battery energy
MWh. The planned level is the scheduler's target for the end of each hour, set by the seven-day plan.
GPUs running and nodes on
GPUs on the 333 leased nodes. Online inference, development and other work run at release; training and offline inference can be deferred. Nodes that are on draw standing power even when idle.
Show the hourly data for this week as a table
What the scheduler does every hour
- Reads what it knows. The latest ECMWF forecast of wind and solar for the next seven days, the battery level, and the tasks that have arrived. It never sees the actual weather of the hours ahead.
- Plans the next seven days. A linear programme chooses battery levels, backup use and how much deferrable work to run and how many nodes to keep on in each hour, at the lowest cost of backup fuel and late work.
- Acts for one hour, then plans again. Only the first hour of the plan is carried out; an hour later the scheduler re-plans with a fresh forecast.
- Runs tasks by deadline. Online inference, development and other work run at release. Training has a completion window of 168 hours and offline inference of 24 hours; the most urgent deferrable tasks start first.
- Switches idle nodes off. Nodes without work are powered down, keeping a few spares on for new arrivals. A node stays on for at least two hours and off for at least one.
- Balances the hour. If supply falls short, it uses the battery down to the planned level, then the backup engines, then the rest of the battery, then pauses deferrable tasks. Only after that is any energy unserved.
The whole of 2024 with this equipment
About these runs
- The site has 350 eight-GPU nodes: 206 with NVIDIA HGX B300 (1,648 GPUs) and 144 with RTX PRO 6000 (1,152 GPUs). 333 nodes are leased and the 17 unleased nodes stay off. Enterprise tenants use about half of what they lease, so 48% of all card-hours have a task running. Every tenant is on a flexible lease, which lets the scheduler defer its training and offline inference.
- The equipment was chosen on 2025 weather as the lowest-cost design that keeps backup fuel within a 10% share of electricity, and is replayed here on 2024, a low-wind year.
- Tasks come from the public record of a multi-tenant GPU cluster (Alibaba), converted to run times on the new cards. Each card's power follows its task's type and measured activity.
- Forecasts are the ECMWF IFS high-resolution runs as published, used eight hours after their base time. Before 5 March 2024 the public archive holds only 10 m wind, so the January week uses wind scaled from 10 m and a statistical solar forecast; its forecasts are less accurate.
- Times are UTC. Outstanding deferrable work is estimated from hourly arrivals and hours run, and includes the remaining hours of tasks already running.